Notification of planned construction activity for 07/21/25 thru 07/27/25:

Roadway Construction plans to perform the following work activities:

  • Grading and paving on Middle Road.
  • Storm drainage improvements on Lakeview Drive.
  • Grading and paving on Gulfstream Road between Lakeview Drive and Old School Road.
  • Road removal, construction of concrete valley gutters, and base installation on Gulfstream Road between Banyan Road and Old School Road.
  • Storm drainage work on Banyan Road between Polo Drive and Gulfstream Road.
  • Storm drainage installations on Gulfstream Road between Old School Road and Sea Road.
  • Water line and service installations at the corner of Gulfstream Road and Sea Road.

Contractor Work Schedule 7/21 - 7/27

Work Area Map

For more information on the project, view the Project Overview.

Stay tuned to the website for future updates.