Notification of planned construction activity for 08/04/25 thru 08/10/25:
Roadway Construction plans to perform the following work activities:
- Construct concrete valley curbs, install the 2nd lift of base, and pave at Lakeview Drive and Banyan Road between Polo Road and Gulfstream Road.
- Install storm drainage and water utilities on Oleander Way.
- Remove road, install base, and construct concrete valley curbs at the North end of Gulfstream Road.
- Pave at the intersection of Old School Road and Gulfstream Road.
- Install water utilities and services on Bermuda Way and Sea Road.
For more information on the project, view the Project Overview.
Stay tuned to the website for future updates.