Notification of planned construction activity for 10-13-25 through 10-19-25:
Roadway Constructions plans to perform the following work activities:
- Continue with storm drainage work on Oleander Way.
- Remove road and install the 1st lift of base rock on Lakeview Drive between Gulfstream Road and A1A.
- Construct concrete valley gutter, install the 2nd lift of base rock, and pave Banyan Road between Lakeview Drive and A1A.
- Construct concrete valley gutter, install the 2nd lift of base rock, and pave Oleander Way North of Banyan Road.
- Remove road and install the 1st lift of base rock on Sea Road between Bermuda Way and A1A.
For more information on the project, view the Project Overview.
Stay tuned to the website for future updates.