Notification of planned construction activity for 11-03-25 through 11-09-25:

Roadway Constructions plans to perform the following work activities:

  • Remove road, construct concrete valley gutters, and install road rock base on Golfview Drive between Polo Drive and A1A.
  • Remove road, construct concrete valley gutters, and install road rock base on Banyan Road between Gulfstream Road and A1A.
  • Remove road, construct concrete valley gutters, and install road rock base on Bermuda Way.
  • Continue with storm drainage work on Oleander Way.

Contractor Work Schedule 11/03 - 11/09