Notification of planned construction activity for 11-10-25 through 11-16-25:
Roadway Constructions plans to perform the following work activities:
- Remove road, construct concrete valley gutters, install road rock base lifts, and assemble water line and services on Golfview Drive.
- Pave Golfview Drive between Gulfstream Road and Polo Drive.
- Continue with storm drainage improvements on Oleander Way.
- Pave Banyan Road between Gulfstream Road and A1A.
- Pave Oleander Way North of Banyan Road.
- Remove road, construct concrete valley gutters, and install road rock base on Bermuda Way.
- Pave Sea Road between Bermuda Way and A1A.
For more information on the project, view the Project Overview.
Stay tuned to the website for future updates.