Overall Project Construction Progress
Anticipated Construction Schedule
| Date | Construction Activity | 
|---|---|
| APRIL 22, 2024 | Initial mobilization: light activity, surveying, setting up Maintenance of Traffic devices, erosion control material delivery | 
| APRIL 24, 2024 | Phase 1 begins at Wright Way with Clearing & Grubbing operations | 
| MAY 03, 2024 | Phase 1 begins at Old School Road with Clearing & Grubbing operations | 
| JUNE 17, 2024 | Removal of existing drainage begins on Polo Drive | 
| JULY 02, 2024 | Watermain & Storm Water installation begins on Polo Drive | 
| AUGUST 21, 2024 | Phase 1 begins at Banyan Road with Clearing & Grubbing operations | 
| NOVEMBER 06, 2024 | Phase 1 begins at Palm Way with Clearing & Grubbing operations | 
| DECEMBER 11, 2024 | Phase 1 begins at Middle Road with Clearing & Grubbing operations to Golfview Drive | 
| Date | Construction Activity | 
|---|---|
| FEBRUARY 16, 2025 | Phase 1 is substantially complete | 
| FEBRUARY 17, 2025 | Phase 2 begins with initial mobilization, light activity, setting up Maintenance of Traffic devices, erosion control material delivery | 
| FEBRUARY 20, 2025 | Phase 2 begins at Gulfstream Road & Golfview Drive with Clearing & Grubbing operations | 
| FEBRUARY 27, 2025 | Watermain & Storm Water installation begins on Gulfstream | 
| MARCH 20, 2025 | Phase 2 begins at Middle Road with Clearing & Grubbing operations | 
| APRIL 17, 2025 | Phase 2 begins at Lakeview Drive with Clearing & Grubbing operations | 
| JUNE 15, 2025 | Phase 2 begins at Banyan Road with Clearing & Grubbing operations (coordinate work near school in summer) | 
| JULY 16, 2025 | Phase 2 begins at Oleander Way with Clearing & Grubbing operations | 
| SEPTEMBER 02, 2025 | Phase 2 begins at Bermuda Way with Clearing & Grubbing operations | 
| OCTOBER 14, 2025 | Phase 2 is substantially complete | 
| OCTOBER 15, 2025 | Final Asphalt placement begins on Phase 1 and Phase 2 | 
| DECEMBER 13, 2025 | Final Completion of the Project | 
Check back for future scheduling updates.
*Schedule subject to change