Notification of planned construction activity 10/28/24 thru 11/03/24:
- The contractor will be performing road removal and installation of the 1st lift of base at Polo Drive.
- The contractor will be installing storm drainage on Polo Drive and Palm Way.
Contractor Work Schedule 10/28 - 11/03
Work Area Map
For more information on the project, view the Project Overview.
Stay tuned to the website for future updates.