Please be advised that Roadway Construction, LLC will not be working on Veterans Day, November 11, 2024.

Notification of planned construction activity 11/12/24 thru 11/17/24:

  • The contractor will continue with storm drainage installations on Palm Way.
  • Roadway Construction will perform waterline & service installations on Banyan Road.
  • The contractor will conduct grading, concrete valley gutter installation, and continue with the 2nd lift of base at Polo Drive.
  • Roadway Construction will work on road removal, storm drainage installations, and placement & compaction of the 1st lift of base at Polo Drive between Old School Road and Banyan Road.

Contractor Work Schedule 11/12 - 11/17

Work Area Map

For more information on the project, view the Project Overview.