Notification of planned construction activity 11/25/24 thru 12/01/24:
- The contractor will continue with water line and service installations on Banyan Road and Palm Way.
- Polo Drive (Old School Rd to Banyan Rd): Storm drainage, pavement removal, concrete valley gutters, and base rock installation by Roadway, LLC.
- Polo Drive (Lakeview Dr to Banyan Rd): Grading, compacting road rock, and paving.
Contractor Work Schedule 11/25 - 12/01
Work Area Map
For more information on the project, view the Project Overview.
Stay tuned to the website for future updates.