Notification of planned construction activity for 12-01-25 through 12-07-25:
Roadway Constructions plans to perform the following work activities:
- Construct concrete valley gutters, install the 2nd lift of base rock, and pave at Sea Road East of Bermuda Way.
- Remove road, construct concrete valley gutters, install road rock base, and pave Banyan Road between AIA and Oleander Way.
- Remove road, construct concrete valley gutters, install road rock base, and pave Banyan Road between AIA and Lakeview Drive.
- Continue with storm drainage improvements on Oleander Way between Lakeview Drive and Banyan Road.
- Remove road, construct 1st lift of base rock, and install storm drainage on Bermuda Way.
- Install waterline and services on Old School Road between Polo Drive and Gulfstream Road.
- Pave at Golfview Drive between Gulfstream Road and AIA.
For more information on the project, view the Project Overview.
Stay tuned to the website for future updates.