Notification of planned construction activity 5/26/25 thru 6/01/25:

  • The contractor will perform road removal, construct concrete valley gutters, and install the first lift of base at Gulfstream Road between Middle Road and Lakeview Drive.
  • The contractor will also work on road removal, construction of water & storm utilities , and install the first lift of road rock on Gulfstream Road between Lakeview Drive and Old School Road.
  • No work will occur on Monday, May 26, 2025, in observance of Memorial Day.

Contractor Work Schedule 5/26 - 6/01