Thursday, July 16
- Crews will complete paving on Polo Drive between Old School Road and Banyan Road.
- The contractor will begin paving Banyan Road between Polo Drive and Gulfstream Road.
Work may continue into Friday 7/17 if not completed Thursday 7/16.
Friday, July 17
- Crews will complete paving on Banyan Road between Polo Drive and Gulfstream Road.
- Paving will then move to Oleander Way, beginning at the far north end near School Road and continuing to Banyan Road.
- Crews will then pave Banyan Road from US 1 to Gulfstream Road.
Monday, July 20
Weather and field conditions permitting, crews are expected to:
- Pave Oleander Way between Banyan Road and Lakeview Drive.
- Pave Lakeview Drive from US 1 to Gulfstream Road.
- If time permits, crews may begin paving Lakeview Drive between Polo Drive and Gulfstream Road.
Tuesday, July 21
Weather and field conditions permitting, crews are expected to:
- Complete paving on Lakeview Drive.
- Begin paving Middle Road between Polo Drive and Gulfstream Road.
- Paving on Gulfstream Road from Golfview Road northward may also begin.
All construction activities and schedules are subject to change due to weather or unforeseen field conditions.
For more information on the project, view the Project Overview.
Stay tuned to the website for future updates.