Monday, July 20
Roadway paving operations will continue on Monday, July 20. Crews will first complete paving on Banyan Road between U.S. 1 and Gulfstream Road, if work is not finished today.
Once Banyan Road is complete, paving operations will move to Oleander Way, beginning at Banyan Road and continuing to Lakeview Drive.
After paving on Oleander Way is finished, crews will begin paving Lakeview Drive between U.S. 1 and Gulfstream Road.
Please use caution when traveling through active work zones and follow all posted traffic controls. We appreciate your patience as these roadway improvements are completed.
All construction activities and schedules are subject to change due to weather or unforeseen field conditions.
For more information on the project, view the Project Overview.
Stay tuned to the website for future updates.