Monday, July 20
Crews have completed paving on Oleander Way between Banyan Road and Lakeview Drive and are currently mobilizing to begin paving Lakeview Drive between U.S. 1 and Gulfstream Road.
Tuesday, July 21
Paving operations are scheduled to continue on Lakeview Drive between U.S. 1 and Gulfstream Road, with crews also paving Lakeview Drive between Polo Drive and Gulfstream Road.
If work on Lakeview Drive is completed as scheduled, crews may begin paving Middle Road between Polo Drive and Gulfstream Road.
Wednesday, July 22
Crews are expected to begin paving Gulfstream Road, starting at Golfview Drive and progressing north to approximatelyMiddle Road.
Thursday, July 23
Paving operations on Gulfstream Road will continue north of Middle Road.
Residents and motorists are encouraged to use caution when traveling through active work zones and follow all posted traffic control devices. We appreciate your patience as these roadway improvements progress.
All construction activities and schedules are subject to change due to weather or unforeseen field conditions.
For more information on the project, view the Project Overview.
Stay tuned to the website for future updates.