Wednesday, July 22
Crews have completed paving the southbound lane of Gulfstream Road to approximately the midpoint between Middle Road and Lakeview Drive.
They plan to begin paving the northbound lane from Middle Road to the same location.
Thursday, July 23
Crews will continue paving Gulfstream Road from just south of Lakeview Drive to Banyan Road.
Friday, July 24
Crews will continue paving Gulfstream Road from the Banyan Road area south to the Old School Road area.
Residents and motorists are encouraged to use caution when traveling through active work zones and follow all posted traffic control devices. We appreciate your patience as these roadway improvements progress.
All construction activities and schedules are subject to change due to weather or unforeseen field conditions.
For more information on the project, view the Project Overview.
Stay tuned to the website for future updates.