Tuesday, July 28
Crews are in the final stages of completing the lift from Gulfstream Road/Sea Road to Bermuda Way.

Wednesday, July 29
Crews will continue paving operations on Sea Road from A1A to Bermuda Way and may also begin paving on Bermuda Way south of Sea Road.

Thursday, July 30
Crews are scheduled to pave Bermuda Way from the south side to the north side of Sea Road, with paving activities nearing completion.

Residents and motorists are encouraged to use caution when traveling through active work zones and follow all posted traffic control devices. We appreciate your patience as these roadway improvements progress.

All construction activities and schedules are subject to change due to weather or unforeseen field conditions.