Notification of planned construction activity for 08/25/25 thru 08/31/25:

Roadway Construction plans to perform the following work activities:

  • Remove road, install the 1st lift of base, and conduct storm drainage work on Gulf Stream Road.
  • Remove road and install the 1st lift of base on Sea Road West of Bermuda Way.
  • Install water line and services on Golfview Drive West of Polo Drive.
  • Remove road, install the 1st lift of base, and install waterline and services on Lakeview Drive East of Gulfstream Road.
  • Install water and drainage utilities on Oleander Way.
  • Remove road, install the 1st lift of base, and conduct storm drainage work on Banyan Road East of Gulfstream Road.

Contractor Work Schedule 8/25 - 8/31

Work Area Map

For more information on the project, view the Project Overview.

Stay tuned to the website for future updates.