Notification of planned construction activity for 08/25/25 thru 08/31/25:
Roadway Construction plans to perform the following work activities:
- Remove road, install the 1st lift of base, and conduct storm drainage work on Gulf Stream Road.
- Remove road and install the 1st lift of base on Sea Road West of Bermuda Way.
- Install water line and services on Golfview Drive West of Polo Drive.
- Remove road, install the 1st lift of base, and install waterline and services on Lakeview Drive East of Gulfstream Road.
- Install water and drainage utilities on Oleander Way.
- Remove road, install the 1st lift of base, and conduct storm drainage work on Banyan Road East of Gulfstream Road.
For more information on the project, view the Project Overview.
Stay tuned to the website for future updates.