Notification of planned construction activity for the next two weeks, 8/26/24 – 9/08/24:

  • The Contractor will continue with storm drainage installations on Golfview Drive headed North on Polo Drive.
  • The Contractor will be installing watermain and services on Palm Way and North Polo Drive.
  • The Contractor will be performing road reconstruction on Wright Way and Old School Road.

Please be advised that the contractor will not be working on Labor Day, Monday, September 2, 2024.

Contractor Work Schedule 8/26 - 9/08

Work Area Map

For more information on the project, view the Project Overview.

Stay tuned to the website for future updates.