Notification of planned construction activity for 09-29-25 through 10-05-25:
Roadway Constructions plans to perform the following work activities:
- Construct concrete valley gutter, install the 2nd lift of base, and pave at Gulfstream Road North of Old School Road.
- Construct concrete valley gutter, install the 2nd lift of base, and pave at Sea Road West of Bermuda Way to Gulf Stream Road.
- Remove road and install the 1st lift of base on Sea Road East of Bermuda Road.
- Remove road and install the 1st lift of base on Banyan Road between State Road A1A and Gulfstream Road.
- Remove road and install the 1st lift of base on Oleander Way North of Banayan Road.
- Remove road and install the 1st lift of base on Lakeview Drive between State Road A1A and Gulfstream Road.
- Conduct storm drainage work on Oleander Way.