Notification of planned construction activity 09/09/24 thru 09/15/24:
- The contractor will continue with storm drainage and waterline & service installations on Golfview Drive headed North on Polo Drive.
- The contractor will be installing storm drainage on Middle Rd.
- The Contractor will be installing water and drainage utilities on Palm Way.
- The contractor will be performing road reconstruction on Wright Way and Old School Road
Contractor Work Schedule 9/09 - 9/15
Work Area Map
For more information on the project, view the Project Overview.
Stay tuned to the website for future updates.