Overall Project Construction Progress

Percent Complete 3%

Anticipated Construction Schedule

Date Construction Activity
APRIL 22, 2024 Initial mobilization: light activity, surveying, setting up Maintenance of Traffic devices, erosion control material delivery
APRIL 24, 2024 Phase 1 begins at Wright Way with Clearing & Grubbing operations
MAY 03, 2024 Phase 1 begins at Old School Road with Clearing & Grubbing operations
JUNE 17, 2024 Removal of existing drainage begins on Polo Drive
JULY 02, 2024 Watermain & Storm Water installation begins on Polo Drive
AUGUST 21, 2024 Phase 1 begins at Banyan Road with Clearing & Grubbing operations
NOVEMBER 06, 2024 Phase 1 begins at Palm Way with Clearing & Grubbing operations
DECEMBER 11, 2024 Phase 1 begins at Middle Road with Clearing & Grubbing operations to Golfview Drive
Date Construction Activity
FEBRUARY 16, 2025 Phase 1 is substantially complete
FEBRUARY 17, 2025 Phase 2 begins with initial mobilization, light activity, setting up Maintenance of Traffic devices, erosion control material delivery
FEBRUARY 20, 2025 Phase 2 begins at Gulfstream Road & Golfview Drive with Clearing & Grubbing operations
FEBRUARY 27, 2025 Watermain & Storm Water installation begins on Gulfstream
MARCH 20, 2025 Phase 2 begins at Middle Road with Clearing & Grubbing operations
APRIL 17, 2025 Phase 2 begins at Lakeview Drive with Clearing & Grubbing operations
JUNE 15, 2025 Phase 2 begins at Banyan Road with Clearing & Grubbing operations (coordinate work near school in summer)
JULY 16, 2025 Phase 2 begins at Oleander Way with Clearing & Grubbing operations
SEPTEMBER 02, 2025 Phase 2 begins at Bermuda Way with Clearing & Grubbing operations
OCTOBER 14, 2025 Phase 2 is substantially complete
OCTOBER 15, 2025 Final Asphalt placement begins on Phase 1 and Phase 2
DECEMBER 13, 2025 Final Completion of the Project

Check back for future scheduling updates.

*Schedule subject to change